Lump Sum

size

1800m2

duration

7 Weeks

address

Level 16 & 17, 133 Castlereagh St, Sydney

data sheet

New CBD Campus

The University of Sydney opened a new purpose built campus in March 2013 delivering leading edge innovative MBA education in the heart of the Sydney CBD. The new facility, located on part level 16 and all of level 17 of 133 Castlereagh St, known as Piccadilly Tower is of world class standard.

Prestigious Environment

Geyer designed the fitout of the tenancies to result in a prestigious but functional campus fit for the highest level of executive management education. The space comprises of a corporate style reception, five lecture rooms and collaborative learning spaces. A structural steel interconnecting stair has been installed between levels 16 and 17 requiring significant slab penetration and relocation of existing services.

Other features include:

  • Timber veneer wall and joinery finishes
  • Special finishes including 3mtr x 1mtr x 3mm floor tiles
  • High end audio visual installation
  • Extensive mechanical and electrical services upgrade

Critical Timeframe

As Project Manager for USYD Confluence appointed Graphite Projects in December 2012 with site works commencing 7 January 2013.

Practical Completion was achieved 28 February 2013 allowing MBA classes to commence 1 March 2013.